  • Installation of traditional substations faced challenges in urban areas due to space constraints.
  • High land acquisition costs made conventional substations economically unviable.
  • Need for auxiliary substations during major events and during repair & maintenance of existing substations.
  • Lack of rapid-response infrastructure to integrate variable renewable energy into the grid.
  • Existing substation models were inflexible for quick relocation or deployment in disaster-affected areas.

Achievements

  • Reduced project timelines with quicker installation and commissioning compared to conventional substations.
  • Enabled deployment as auxiliary substations for events and during maintenance of existing substations.
  • Enhanced safety and reliability through factory-built and pre-tested units.
  • Supported grid flexibility by balancing renewable energy fluctuations in real time.
  • Provided a scalable and replicable solution for space-constrained urban zones under APCPDCL’s jurisdiction.

SKOCH Award Nominee

Category: Government Undertaking
Sub-Category: Government Undertaking
Project: Construction of 33/11kV Containerised Substations
Start Date: 1-01-2025
Organisation: Andhra Pradesh Central Power Distribution Corporation Limited
Respondent: Pogaku Pulla Reddy
https://www.apcpdcl.in/
Level: Executive Plus


For more information, please contact:
Pogaku Pulla Reddy at cmd.cpdcl@apcpdcl.in


(The content on the page is provided by the Exhibitor)

Leave a Reply

Back to top button

Adblock Detected

Please disable your Adblocker or whitelist our site to continue.